Delayed Zhanaozen Gas Plant Promised for 2027 Launch
AI-generated illustration
KazMunayGas chair Askhat Khasenov has explained how construction of the gas processing plant in Zhanaozen is progressing. Earlier, President Kassym-Jomart Tokayev criticized the government over the slow pace of work on major projects, Orda.kz reports.
According to Khasenov, the project differs from standard construction because the plant is being assembled on a modular basis. Most of the equipment is manufactured at the producer’s factory and will then be delivered to the site.
The plant has a distinctive feature — modular assembly. The main production is taking place at the manufacturer’s factory. There are 259 items in total. About 49 % of the equipment, or 92 items, has already been manufactured, while 167 items are still in production, Khasenov said.
He said he personally visited the manufacturer’s production facilities. According to the head of KMG, the modular approach will reduce the amount of construction and installation work needed at the site compared with conventional construction. Khasenov said the project is under constant control and that the schedule is being followed.
Under the contract, the EPC contractor must complete the main work in February–March 2027. Commissioning will begin after that and may take up to six months.
Under the contract, February–March is the deadline for the EPC contractor to complete all work. Then commissioning will follow. In 2027, commissioning may take up to six months,the head of KMG said.
Earlier, Tokayev criticized the government over delays in important infrastructure and industrial projects, including in monotowns. In Zhanaozen, which depends on the oil and gas industry, the launch of the gas processing plant is seen as one of the projects needed for the city’s further development and for reducing social tension.
Original author: Ilya Astakhov
Read also:
- Where In Kazakhstan It Is Hardest To Breathe — New Pollution Rating
- Rumors Resurface About Government Reshuffle as Criticism Mounts
- Workers Strike Again in Kazakhstan’s Oil Region
Latest news
- Will Tokayev Get Another Term? Court Says New Constitution Allows Him to Run
- WHO Data Shows 56 % of Kazakh Adults Are Overweight
- Kyrgyzstan Turns to Astana for Gasoline Supplies
- Delayed Zhanaozen Gas Plant Promised for 2027 Launch
- Russia Has Not Requested Fuel Purchases, Energy Ministry Says
- Kazakhstanis Allowed to Hang National Flag on Balconies
- Shooting on Kyrgyzstan-Uzbekistan Border: 27 Security Officers Detained
- Bolat Nazarbayev’s Former Stepson Bought $35.5 Million U.S. Estate for $10
- “Go to Issyk-Kul”: Bishkek Residents Asked to Leave City During SCO Summit
- Kazakh Officials Want to Ban Imported Apples
- Tokayev Congratulated Kazakhstanis On Capital Day And Nazarbayev On His Birthday
- Tourists From Kazakhstan Stuck in Kyrgyzstan Valley After Bridges Washed Away
- Almaty Ranked More Expensive Than Astana in Global Cost of Living List
- Almaty Region Puts High-Risk Mountain Lakes Under Constant Watch
- Kazakhstan and Six Other OPEC+ Countries Support Oil Production Increase
- Kazakhstan’s Respublica Party Keeps Chairman Before New Parliament Election
- Eroded Roads and Evacuations: Almaty Region Deals With Flood Aftermath
- Kazakhstan Steps Up Checks on Gas Stations and Mini-Refineries Amid Fuel Market Controls
- Withered Trees Instead Of Greenery: What Almaty Got After Sairan’s Costly Reconstruction
- Kazakhstan Sends Delegation to Iran for Farewell to Supreme Leader