The Supreme Audit Chamber (SAC) audited the Treasury Committee, which engages in the main tasks of managing the national and local budgets, Orda.kz reports.
It revealed that the treasury system operates with violations that could lead to significant financial losses.
SAC reported that the chamber summed up the audit results.
The current SAC Head, former Prime Minister Alikhan Smailov, noted that the treasury committee was initially created to manage the Republican budget effectively.
Its authority has been expanded: it services the execution of local budgets, the National Fund, and the Victims' Compensation Fund, and handles centralized state purchases. Today, the Committee's territorial bodies serve over 15,000 clients.
However, it makes notable mistakes in managing budget finances and making payments.
One such miscalculation may have cost the state tens of billions of tenge.
The Treasury Committee, in violation of the norms of the Budget Code, issued securities in excess of the originally planned volume in certain months of 2021-2023. Although the outlook for the balance of funds in the cash control account of the republican budget was positive. This led to possible budget losses in the amount of more than 124 billion tenge, The SAC emphasized.
The Committee was also blamed for insufficient oversight over payments for construction projects financed from the budget.
The treasury only requires a contractor to have one supporting document — and it doesn't matter whether it complies with the law or has a note regarding the designer and technical supervision.
In Almaty, the local treasury department paid the contractor twice for reconstructing an administrative building using the same certificate. The company received 3.7 billion tenge, although the cost was lower — 2.5 billion tenge.
Advances to contractors were also paid excessively. Even in cases where tender executors had outstanding advances from previous years, they were given funds "in advance" again.
In addition, the Committee cannot always supervise the targeted budget funds, the entirety of tax payments, etc.
Due to miscalculations in this area, there is a risk that unscrupulous subcontractors will receive profitable government contracts.
The audit revealed 70 procedural violations and 15 systemic deficiencies.
The Committee was ordered to fix them all.
Alikhan Smailov also requested that the treasury improve its information system. This will allow for automatic blocking of payments that are carried out in violation of the law.
Original Author: Nikita Drobny
Latest news
- Kazakhstan Cancels Exam Results For More Than 700 University Applicants
- Astana LRT Operator Looks For Funding In China
- Smoke From Russian Wildfires Reaches Eastern Kazakhstan
- Kazakhstan Offers EU A Broader Partnership In Eurasia
- Oil Leak Reported In Caspian Sea Near Azerbaijan Coast
- Kazakhstan To Build 250 Roadside Service Stations For 180 Billion Tenge
- Police Chase With Kazakh Driver In Phuket Ends In Crash And Injuries
- Foreigners Moving To Kazakhstan Are Choosing Big Cities Over Most Regions
- Turkestan Region Leads Kazakhstan In Twin Births
- From Grain To AI: What Kazakhstan Brought To Afghanistan
- Helicopters Drop 39 Tons Of Water On Forest Fire In East Kazakhstan
- Kazakhstan Tightens Border Checks Despite Saying There Is No Fuel Shortage
- Kazakhstan Seeks Greek Investment In Energy And Transport
- Global Rating Agency Confirms Kazakhstan’s Investment-Grade Status
- Kazakh Company Sent $16 Million To China, Got No Goods And A Huge Fine
- Kazakh Parties Are Losing Focus With Overly Broad Programs, Expert Says
- Almaty Man Registered 990 People In One-Room Apartment And Received Sentence
- Montenegro President Makes First Official Visit To Kazakhstan
- Gas Prices In Kazakhstan To Rise From July 1
- Kazakhstan’s Oldest Gold Mining Company Resold For 8.7 Billion Tenge